Business Park Resurfacing Program

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

General Information

  • Start Date: June 2024
  • Est. Completion Date: Mid-September 2024
  • Location: Various Streets Throughout Business Park. See Below.
  • Project Cost: $1,
  • Contractor: Builders Paving, LLC
  • Project Impacts:
    • Moving Daily Lane Closures
    • Temporary Sidewalk Closure
    • Construction Vehicle Presence

Project Description

The construction activities for the business park resurfacing program are generally broken down into four phases:

Phase I (Storm Sewer) – Necessary repairs and/or modifications are made to the drainage structures along these roadways.

Phase II (Concrete) – Replacement of deteriorated curbs and sidewalks throughout the project area takes place. This work is generally limited to one side of the street at a time.

Phase III (Pavement) – The final phase includes full depth pavement patching, milling of the existing pavement surface, paving the new asphalt surface and the painting of pavement markings. Friendly reminder:  A tack-coat of fresh oil is applied prior to laying the new pavement layer as an adhesive or bonding agent between the asphalt layers. Fresh oil signage will be posted in advance to remind motorist to travel slowly on the tack-coat material.

Phase IV (Restoration) – Final restoration of all disturbed areas to be completed.

The following 2.9 miles of roadways in the Business Park are anticipated to be resurfaced starting in June and completed by mid-September:

  • Arthur Avenue, Elmhurst Road to Busse Road
  • Bonnie Lane, Howard Street to Landmeier Road
  • Lunt Avenue, Elmhurst Road to Busse Road
  • Nicholas Boulevard, Higgins Road to Landmeier Road
  • Nicholas Boulevard, Devon Avenue to Arthur Avenue

Project Updates

September 13, 2024: This week, The Village removed the pavement around the tracks on Lively Boulevard between Mark Street and North Thorndale Road. Progressive Rail raised the tracks to allow a smoother drive over the crossing. The Village then placed asphalt around the newly adjusted tracks.  

September 6, 2024: Next week, The Village in partnership with Progressive Railroad will be reconstructing the two sets of railroad tracks and the asphalt pavement around the tracks on Lively Boulevard between North Thorndale Avenue and Mark Street.  This work will provide smoother travel over the tracks at these locations. Work will begin on Monday, September 9th and will last about one week. During construction, Lively Boulevard will be closed at both railroad crossing locations. However, access to all business will be available by utilizing, Carl Boulevard, Katherine Way, or Kirk Street. Southbound traffic on Lively can utilize Busse Road to access North Thorndale Avenue. 

July 19, 2024: This week, asphalt work finished on Nicholas Boulevard between Landmeier Road and Higgins Road and Bonne Lane. Patching and milling were completed on the streets and the roads will be resurfaced overnight between Friday and Saturday. 

July 12, 2024: This week, concrete work finished on Nicholas Boulevard between Landmeier Road and Higgins Road and Bonne Lane. Lunt Avenue and Arthur Avenue were milled and paved as well. Next week, patching will begin on Nicholas Boulevard and Bonnie Lane.

June 28, 2024: This week, concrete work continued with placing new sidewalk and curb on Nicholas Boulevard between Landmeier Road and Higgins Road, and on Lunt Avenue and Bonnie Lane. The sewer contractor also adjusted the water valve vaults on Lunt Avenue. Next week, concrete removals and pouring new concrete will continue on Nicholas Boulevard and Bonnie Lane, while pavement patching and milling will begin on Arthur Avenue. 

June 21, 2024: This week, concrete work continued with the placing of new sidewalk and curb on Arthur Avenue and Lunt Avenue, while removals began on the west side of Nicholas Boulevard between Landmeier Road and Higgins Road. The sewer contractor also installed a new inlet on Lunt Avenue. Next week, concrete removals and pouring will continue on Lunt Avenue, Arthur Avenue, and Nicholas Boulevard.

June 14, 2024: This week, concrete work continued with the placing of new sidewalk and curb on Arthur Avenue, Nicholas Boulevard, and Lunt Avenue. The contractor also continued curb and sidewalk removals on the opposite side of Arthur Avenue. Next week, concrete removals and pouring will continue on Lunt Avenue, Arthur Avenue, and Nicholas Boulevard.

June 7, 2024: This week, work continued with the removal of sidewalk and curb on Arthur Avenue, Nicholas Boulevard, and Lunt Avenue. The contractor also poured the new curb and sidewalk on Arthur Avenue. Next week, concrete removals and pouring will continue on Lunt Avenue and Bonnie Lane.

May 31, 2024: This week, work began on the Business Park Rehabilitation Program with the sewer contractor reconstructing and installing new inlets. This year’s program also consists of resurfacing streets, pavement patching, rehabilitation of deteriorated curb and sidewalk, and improvements to ADA curb ramps.  This project is located on multiple streets within the Village’s Business Park and consists of a total project length of 2.9 miles.