Elk Grove Village
HOME MenuGateway Signs - Business Park
General Information
- Start Date: September 2022
- Est. Completion Date: November 2022
- Location: Various Locations
- Project Cost: $826,000
- Contractor: Schaefges Brothers Inc.
- Project Impacts:
- Daily lane closures
- Construction Vehicle Presence
Project Description
The Gateway Signs Business Park Phase II project will provide site improvements at two gateway sign locations within the Business Park. The location of these signs are the southwest corner of Elmhurst Road and Landmeier Road, and at our southern Village limits on Busse Road. The Village will also remove signs made redundant by other welcoming markers and that have served their time. These signs are located along Higgins Road just east of Arlington Heights Road, the intersection of Higgins Road and Oakton Street, and at Busse Road just south of Oakton Street.
Project Updates
December 16, 2022: This week, the gateway signs were installed at the southwest corner of Elmhurst Road and Landmeier Road, and in the median at our southern Village limits on Busse Road. The gateway sign in the Busse Road median will be illuminated by solar panels. The gateway sign at Landmeier Road and Elmhurst Road will be illuminated once the connection with ComEd is complete.
November 11, 2022: This week, the contractor installed landscaping around the new gateway signs at Landmeier Road and Elmhurst Road, as well as in the median on Busse Road.
October 21, 2022: Helix foundations for new gateway signs were installed this week at Landmeier Road and Elmhurst Road, as well as the median on Busse Road. Work will continue on the irrigation systems next week.
October 14, 2022: This week, the contractor continued to install the water service line in the Busse Road median to provide the infrastructure for an irrigation. Next week, work will continue on the irrigation systems.
October 7, 2022: This week, the contractor directionally drilled a water service under Busse Road to provide the water infrastructure for an irrigation system in the landscaped median. Next week, work will continue as the irrigation systems are installed.
September 30, 2022: This week, the contractor began to provide the infrastructure to install new irrigation systems around the locations of the two new gateway signs at Elmhurst Road at Landmeier Road and Busse Road at the Village limits. Next week, work will continue as water and electric service lines will be run to these sites.